Skip to content
NOWCAST WXII 12 News at 6 am Sunday
Live Now
Winston-Salem, NC27101
57°
Fair
Chance of precipitation 30%
MORE
1 / 1
Advertisement

NCDOT say portions of Winston-Salem Beltway are complete; more segments under construction

The beltway allows drivers to circumnavigate around the city and help decongest traffic around the city.

NCDOT say portions of Winston-Salem Beltway are complete; more segments under construction

The beltway allows drivers to circumnavigate around the city and help decongest traffic around the city.

WORK ZONES, BUT A LITTLE BIT OF GOOD NEWS FOR DRIVERS. THE STATE DEPARTMENT OF TRANSPORTATION SAYS WORK ON THE WINSTON-SALEM BELTWAY PROJECT IS ON SCHEDULE. WXII’S ADRIANNA HARGROVE FOUND OUT CREWS HAVE EVEN COMPLETED SOME PORTIONS. SHE HAS MORE ON WHAT CREWS ARE FOCUSED ON NOW. JOHN RYAN WITH NCDOT SAYS IT’S BEING DONE IN PHASES. ONCE THEY GET FUNDING APPROVED, THEY GET TO WORK ON THOSE SECTIONS, WHICH IS WHY NCDOT DOESN’T HAVE A TIMELINE ON WHEN THE ENTIRE BELTWAY PROJECT WILL BE COMPLETE. WE ARE WRAPPING UP THE NORTHERN PIECE, OUR EB SECTION THAT TIES IN 74 TO 52. THAT SHOULD BE DONE HOPEFULLY BY THE END OF THE MONTH. THEY’RE PUTTING THE FINAL TOUCHES ON THAT RIGHT NOW. THERE ARE TWO PIECES ON THE SOUTHERN END THAT TIE. THREE 1174 COMING OUT OF HIGH POINT. AND THAT WILL ALLOW FOLKS COMING OUT OF HIGH POINT TO CATCH THE BELTWAY AND TRAVEL ALL THE WAY NORTH AROUND THE 52. WHEN THOSE TWO ARE COMPLETE, THOSE ARE BOTH WELL OVER 60% COMPLETE AT THIS POINT. CONTRACT COMPLETION IS IN 2027. RYAN SAYS WORK ON THE TWO SECTIONS OF THE BELTWAY FROM U.S. 421 TO UNIVERSITY PARKWAY AND UNIVERSITY PARKWAY TO HIGHWAY 52, ARE FINISHED ON THE WESTERN SIDE OF WINSTON-SALEM. THE SEGMENT OF HIGHWAY 52 TO REYNOLDS ROAD IS IN THE DESIGN PHASE. THAT AREA WILL START CONSTRUCTION IN 2029. CONSTRUCTION ON THE PORTION FROM RINALDO ROAD SOUTH TO ROBINHOOD ROAD WILL START IN 2030. NOW, NCDOT SAYS THE BELTWAY’S MAIN FUNCTION IS TO ALLOW DRIVERS TO CIRCUMNAVIGATE THE CITY. CONSTRUCTION STARTED TEN YEARS AGO, MAKING IT DIVISION NINE’S LONGEST PROJECT TO DATE. IN STUDIO, ADRIANN
Advertisement
NCDOT say portions of Winston-Salem Beltway are complete; more segments under construction

The beltway allows drivers to circumnavigate around the city and help decongest traffic around the city.

Officials with the North Carolina Department of Transportation said crews have completed some portions of the Winston-Salem Beltway and are now focused on the northern and southern ends.The beltway allows drivers to circumnavigate around the city and help decongest traffic around the city.John Rhyne with the NCDOT says more and more pieces of the beltway are coming together with some pieces of the beltway set to be complete this year and some pieces that have not yet started.Rhyne says a section of the beltway from US-421 up to University Parkway and from University Parkway to Highway 52 has also been completed.Other parts of the beltway remain under construction."We're wrapping up the northern piece the section that ties I-74 to Highway 52 that should be done hopefully by the end of the month," Rhyne adds. "They're building the final touches on that right now. There are two pieces on the southern end that tie US-311 and I-74 coming out of High Point will allow folks coming out of High Point to catch the beltway and travel all the way north around Highway 52 when those two are complete. Those are both well over 60% complete at this point and contract completion is 2027."Rhyne says construction for Highway 52 to NC-67 is set to begin in 2030, and construction from NC-67 to Robinhood Road is set to begin in 2031. NCDOT started construction on the beltway 10 years ago, making it NCDOT Division 9's longest project to date.

Officials with the North Carolina Department of Transportation said crews have completed some portions of the Winston-Salem Beltway and are now focused on the northern and southern ends.

The beltway allows drivers to circumnavigate around the city and help decongest traffic around the city.

Advertisement

John Rhyne with the NCDOT says more and more pieces of the beltway are coming together with some pieces of the beltway set to be complete this year and some pieces that have not yet started.

Rhyne says a section of the beltway from US-421 up to University Parkway and from University Parkway to Highway 52 has also been completed.

Other parts of the beltway remain under construction.

"We're wrapping up the northern piece the section that ties I-74 to Highway 52 that should be done hopefully by the end of the month," Rhyne adds. "They're building the final touches on that right now. There are two pieces on the southern end that tie US-311 and I-74 coming out of High Point will allow folks coming out of High Point to catch the beltway and travel all the way north around Highway 52 when those two are complete. Those are both well over 60% complete at this point and contract completion is 2027."

Rhyne says construction for Highway 52 to NC-67 is set to begin in 2030, and construction from NC-67 to Robinhood Road is set to begin in 2031.

NCDOT started construction on the beltway 10 years ago, making it NCDOT Division 9's longest project to date.